Velardena MillingTwo mills are currently operating at Velardeña:

  • An oxide mill, which presently has a capacity of 500 tpd and produces gold/silver doré bars

  • A sulfide mill, which presently has a capacity of 320 tpd capacity and produces lead, zinc and pyrite concentrates

 

 

Production is expected to increase as shown in the following forecast:

Production (payable metals) Q4 2011 Q1 2012 Q2 2012 Q3 2012 Q4 2012
Au (oz) 1,000 2,000 3,000 4,000 4,000
Ag (oz) 42,000 73,000 120,000 185,000 214,000
Pb (lbs) 23,000 38,000 59,000 87,000 101,000
Zn (lbs) 51,000 85,000 131,000 193,000 223,000

 

  